South Perth Station Precinct works update: week commencing 13 February 2017
Approved works within the South Perth Station Precinct for the week commencing 13 February 2017:
Location | Details of works | Who | Date | Time |
96 Mill Point Road | Excavation works resulting in increased truck movements on Harper Terrace and South Perth Esplanade. | Aurelia / Hanssen | 13 - 17 February | 7am to 5pm |
Labouchere Road (Mill Point Road - Mends Street) | Southbound lane closure to support dewatering truck movements, currently operating 24 hours a day, 7 days a week. | Civic Heart / Hanssen | 13 - 17 February | 24 hours |
20 Harper Terrace | Internal works on site with management of pedestrians when footpath obstructions occur. | Cooktown Constructions | 13 - 17 February | 7am to 5pm |
Short term, low impact works
Location | Details of works | Who | Date | Time |
Mill Point Road (north) - Millers Pool | Lane closure for Millers Pool works. | City of South Perth | 13 - 17 February | 7am to 5pm |
Mill Point Road & Labouchere Road | Banner change over in central median - works to be scheduled to minimise traffic impacts. | City of South Perth | TBC | TBC |
Emergency works (on-going unplanned works)
Location | Details of works | Who | Date | Time |
Mill Point Road (Harper Tce - Mends St) |
Lane closure eastbound to facilitate water removal operations. |
Western Power |
13 - 17 February |
24 hours |
Mill Point Road (North) & Labouchere Road | Lane closures to facilitate sewer system cleaning operations. | Water Corporation Contractors | Ongoing | 7am to 5pm |
Upcoming works (details to be confirmed)
Location | Details of works | Who | Date | Time |
96 Mill Point Road | Closure of Harper Terrace to facilitate concrete pours on Aurelia Site | Aurelia / Hanssen | 20 - 24 February, 1 March & 3 March | 7am to 5pm |
Mends Street & Labouchere Road | Installation of upgrade to existing gas main | ATCO Gas | TBC (likely commencement late February 2017) | 7am to 5pm |
Labouchere Road; Mill Point Road and Harper Terrace | Water main upgrade works | Water Corporation Contractors | TBC (likely commencement late March 2017) | 7am to 5pm |