South Perth Station Precinct works update: week commencing 30 January 2017
Approved works within the South Perth Station Precinct for the week commencing 30 January 2017:
Location | Details of works | Who | Date | Time |
100 Mill Point Road | Lane closures eastbound on Mill Point Road near Harper Terrace and southbound on Labouchere Road near Bowman Street due to Emergency Works. | Western Power | 30 January - 5 February | 24 hours a day |
96 Mill Point Road | Excavation works resulting in increased truck movements on Harper Terrace and South Perth Esplanade | Aurelia/Hanssen | 30 January - 4 February | 7am to 5pm |
20 Harper Terrace | Internal works on site with management of pedestrians when footpath obstructions occur | Cooktown Constructions | 30-31 January | 7am to 5pm |
20 Harper Terrace | Delivery and installation of concrete panels. Crane onsite and trucks on road with pedestrian management in place (subject to revised Traffic Control Diagram submission) | Cooktown Constructions | 1 February | 7am to 5pm |
20 Harper Terrace | Concrete pour on site, trucks accessing the site under traffic control. Pedestrian management in place (subject to revised Traffic Control Diagram submission) |
Cooktown Constructions |
2 February | 7am to 12pm |
Upcoming works (details to be confirmed)
Location | Details of works | Who | Date | Time |
96 Mill Point Road |
Closure of Harper Terrace to facilitate concrete pours on Aurelia Site |
Aurelia/Hanssen |
16, 18, 21 & 23 February 1 & 3 March |
7am to 5pm |
Mends Street & Labouchere Road | Installation of upgrade to existing gas main | ATCO Gas | TBC | 7am to 5pm |
Contact us
- Phone 9474 0777