Underground Power

The City’s vision is to have overhead power lines placed underground throughout the entire City and we are well underway to achieving this goal with works on three Round Six project areas having commenced. 

The State Underground Power Program (SUPP) replaces overhead power lines with underground power infrastructure. The Program is a partnership between the State Government, Western Power and local government and is administered by Energy Policy WA (formerly known as the Public Utilities Office). 

In January 2017, it was announced that funding had been secured for three more City of South Perth projects - Manning, Collier and South Perth. 

The City will monitor future funding rounds of the SUPP with a view to nominate other areas within the City for the program including Kensington.

News Listings

April 2025
SouthPerthstreet

Underground power update - Kensington

News Update 10 April 2025

Western Power has provided an update on the estimated completion date for the Kensington underground power project.

Underground Power
Cardrivingdownatreelinedstreet

Underground power update for South Perth and Hurlingham

News Update 10 April 2025

Western Power has provided an update on the estimated completion date for the South Perth and Hurlingham underground power project.

Underground Power
December 2024

South Perth and Hurlingham underground power update

News Update 18 December 2024

The underground power project in the South Perth and Hurlingham areas is now scheduled for completion in June 2025.

Underground Power

Find out more

Sign up for the City's eNewsletter to stay in touch about this project.

For questions related to the timing of the projects, site reinstatement or construction related activities, please contact Western Power at undergroundpower@westernpower.com.au

More information and frequently asked questions are available on the Western Power website

For information about the State Underground Power Program in general, visit the Public Utilities Office website.