South Perth and Hurlingham Project Area

Map of the Collier underground power area

Underground Power has come to the South Perth and Hurlingham areas through the Retrospective Undergrounding Project (RUP).

This project is replacing overhead power lines with underground power infrastructure to move closer towards the City's vision for underground power in all of its suburbs. The RUP is a partnership between the City and Western Power.

Construction in the South Perth and Hurlingham project areas commenced in October 2022 and is scheduled for completion by 31 July 2025.

 

Background

The South Perth project area was initially assessed for underground power in 2017 within Round Six of the State Underground Power Program (SUPP). Hurlingham was not eligible for consideration as a SUPP as the area contained less than 500 properties (the minimum amount required for a SUPP). Instead, the City nominated this area as a RUP, which has lower qualification requirements, to ensure this community was included.

In 2020 Western Power finalised estimates for the South Perth SUPP and the Hurlingham RUP, and determined that amalgamating these two project areas and delivering the entire project as a RUP was the most appropriate path forward.

 

What you can expect

Stage 1 - Property Services Installation

Stage 2 - Street Services Installation

Stage 3 - Changeover 

Stage 4 – Removal of poles and wires

Stage 1 and 2 of the project works have been completed. Stage 3 and 4 are being completed concurrently, transitioning properties to underground power as efficiently as possible. These stages involve changeover works to switch properties to the underground service (occupiers will be notified a few days beforehand detailing what this process means for them).

Once properties are connected to underground circuits, poles and wires will be removed. Some poles and wires will need to remain where they are servicing other streets not yet underground. 

 

Who to contact

For any project repairs or reinstatement enquiries, please contact Mainswest on 08 9303 1540 or email sph.rupp@mainswest.com.au.

For other project enquiries, please visit the Western Power website or call them on 13 10 87.

 

Related documents

News Listings

May 2022
UndergroundPower_0000s_0009_IMG_0324

Underground Power - Community Information Session, Wednesday 25 May 2022

News Update 23 May 2022

Property owners in the South Perth and Hurlingham area will be able to find out more about the City's next underground power project at a Community Information Session on Wednesday 25 May 2022.

Underground Power
March 2022
Neighbourhood4

Underground Power update

News Update 4 March 2022

Underground power is one step closer in the South Perth and Hurlingham project areas.

Underground Power
December 2021
UndergroundPower_0000s_0008_IMG_0335

State Underground Power works over Christmas

News Update 21 December 2021

The Western Power State Underground Power Project (SUPP) contractor Genus will stop work on site for the Christmas break from Tuesday 21 December 2021 until Wednesday 5 January 2022.

Underground Power
November 2021
UndergroundPower_0000s_0003_IMG_0404

Collier and Manning State Underground Power progress

News Update 23 November 2021

The State Underground Power project in the Manning and Collier areas is progressing well with completion on schedule for mid 2022.

Underground Power