Road rehabilitation works

Every year the City identifies roads within our community that are in need of rehabilitation, including repairs to the road surface and surrounding infrastructure, in order to prevent any further deterioration and avoid costly repairs in the future.

The road works can include:

  • Road resurfacing (with asphalt)
  • Kerb replacement
  • Drainage structure upgrades
  • Minor footpath upgrades.

Frequently Asked Questions

Ongoing road rehabilitation works

News Listings

November 2016
_JC_5747

Road Rehabilitation Works, Lowan Loop in Karawara

News Update 28 November 2016

From 30 November, the City will be undertaking road rehabilitation works in Karawara along Lowan Loop at both intersections with Walanna Drive.

Road Works
Neighbourhood1

Road rehabilitation works on Market Street and King Street, Kensington

News Update 28 November 2016

From 5 December, the City will be undertaking road rehabilitation works along Market Street between Douglas Avenue and Collins Street and along King Street between Market Street and Collins Street in Kensington.

Road Works
Neighbourhood4

Works on Hovia Terrace between Canning Highway and Third Avenue

News Update 1 November 2016

Road rehabilitation works are scheduled to start the week commencing 7 November 2016 and estimated to take approximately 3 weeks.

Road Works
October 2016
_JC_5745

Upcoming works in your neighbourhood

News Update 26 October 2016

Upcoming road works, pavement rehabilitation, stormwater drainage and traffic management in the City of South Perth.

Road Works
trafficmanagement

New roundabout for Mt Henry Road and Hope Avenue intersection

News Update 24 October 2016

The City intends to install a roundabout at the intersection of Mt Henry Road and Hope Avenue in Salter Point to improve access through the junction during periods of high traffic flow.

Road Works
CapitalWorksProgramme2

Closure of section of footpath on Labouchere Road

News Update 20 October 2016

The footpath and verge on the west side of Labouchere Road adjacent to 32-34 Charles Street will be closed from Monday, 24 October to Friday, 15 December 2016.

Road Works
Parking

Carpark upgrade works at Challenger Reserve

News Update 10 October 2016

The City will be undertaking upgrade works within the Challenger Reserve carpark located adjacent to Challenger Avenue. The works are scheduled to start the week commencing 10 October 2016 and take approximately 3 weeks to complete, weather permitting.

Road Works
September 2016
Neighbourhood4

Footpath works during September, October & November

News Update 16 September 2016

In accordance with the 2016/2017 Capital Works Program, the City will carry out footpath works during September, October and November.

Road Works
_JC_5745

Works in Your Neighbourhood

News Update 1 September 2016

The following works are scheduled for October, November and December.

Road Works
July 2016
CapitalWorksProgramme2

Works in Your Neighbourhood

News Update 1 July 2016

Road works scheduled for July, August and September 2016.

Road Works